GROUP: |
Mechanical |
TYPE: |
Elevator |
SUB-TYPE: |
Commercial |
PRIMARY USE: |
N/A |
WORK DESCRIPTION: |
Installation of Verticle platform lift |
PERMIT ISSUED: |
Yes |
PERMIT ISSUE DATE: |
03/25/2014 |
ISSUING OFFICE: |
Metro |
CURRENT STATUS: |
Permit Finaled |
CURRENT STATUS DATE: |
10/06/2014 |
|
|
Submitted |
03/06/2014 |
APPLICANT |
Assigned to Plan Check Engineer |
03/13/2014 |
CALVEN HSU |
Corrections Issued |
03/17/2014 |
CALVEN HSU |
Quality Review Completed |
03/17/2014 |
DOMENICO BARBATO |
Mechanical Plans Picked Up |
03/20/2014 |
APPLICANT |
Plan Check Approved |
03/25/2014 |
CALVEN HSU |
Issued |
03/25/2014 |
LADBS |
Permit Finaled |
10/03/2014 |
JESSE LEYVA |
|